As announced our next scheduled sailing will be on Friday 17th February 2023.  The vessel will depart Penzance with Boojum Bay tug, continuing to assist for this sailing.

The crew will unload all freight on St Mary’s on Saturday 18th February 2023 and aim to return to Penzance the same day.

The repair on the tail shaft and propeller is in progress. Please be assured that we are doing everything we can to expedite this work and we’d like to thank you for your continued understanding.

Once the repair has been completed, the Gry Maritha will be dry docked to fit the tail shaft and propeller. We aim to dry dock the Gry Maritha during the week commencing, 20th February 2023. The exact timing of the docking is yet to be confirmed, pending completion of the tail shaft repairs, suitable weather conditions for docking and completion of repair work on a vessel that is currently occupying the dock.

During the next 48hrs we will have a better overview for next week’s schedule and will release further updates by Thursday 16th February 2023.

Due to further disruption anticipated next week, we would recommend that orders for food and perishable items are placed accordingly for Friday’s sailing (17th) where availability allows.Please be assured that we are working as a priority to resolve this issue as quickly as possible.

We would like to take this opportunity to thank you for your patience and understanding and we apologise for the inconvenience. Please contact Penzance Quay on 01736 334249 or St Mary’s Quay on 01720 424230 with any queries.

Please keep an eye out for updates via email, our text alerts and on our Twitter travel updates page and website.